Thursday, August 27, 2009

Progress..

27/8
1) completed chapter 2 & 3.. Passing up the paper work on next tuesday..
2) progessing on chapter 4.. Finish a quarter part of it.. Should be finish before next week..

Thursday, August 20, 2009

meeting

20/8 - met with cik hazinah
1) guided us how to do a correct report from chapter 1 to 5
2) realize done many mistakes.. ( correction is in progress)
3) not fully confident which model to use in Methodology. (might use Waterfall..) anyone have idea?
4) haven completed the use case, sequence diagram.. (drafting..)

Tuesday, August 11, 2009

11/8 FYP Progress

1. met cik hazinah for about 40 minutes to discuss about the state diagram, use case and architecture design.

2. met with the technician (En. Azlan) to have a discern look at the fingerprint device.

3. Still progressing for both chapter 2 & 3.

4. Probably goin to miss the presentation on thursday.

Sunday, August 9, 2009

Chapter 2 progress

10/8
1) complete 1st half of chapter 2. Going to search for more information regarding technologies, programming tools, suitable database and server that to be used..

2) going to find the technician to have a view at the fingerprint device.

3) found out fingerprint programming could be done with ASP.Net

4) working on the gantt chart

5) by today, the report sent were chapter 1 and technology report.

Thursday, August 6, 2009

1st formal meeting

6/8 - Had meeting with Cik Hazinah. Task was given to complete in 1 week time. The tasks are :

1. Gantt Chart for both PSM1 & 2

2. Chapter 2 & 3 report writing

3. Find similar & existing system as reference

4. Informal presentation on Thursday - 9.30am